Ferry system electrification

Tokitae out on the harbor

Major Project overview

Washington State Ferries (WSF) will rebuild and modernize our fleet and convert our system, the largest in the country, to hybrid-electric power by 2040 following direction from the Washington legislature and governor. Rebuilding the fleet is necessary to ensure reliable ferry service. Transitioning to a hybrid-electric fleet is necessary to reduce emissions, ensure resiliency, and reduce operations and maintenance costs.

As the biggest contributor of greenhouse gas emissions among Washington state agencies, WSF burns approximately nineteen million gallons of diesel fuel to support nearly twenty million passengers every year. This innovative electrification program will drastically reduce greenhouse gas emissions and save millions in fuel costs.

Timeline overview

2020-2040

Major project status

Construction

Funding

$1.68 billion secured funding | $3.98 billion total estimated cost

Major project alerts

Gov. Bob Ferguson announced that Eastern Shipbuilding Group was awarded the contract to build three new hybrid-electric 160-auto ferries.

WSF aspires to a reliable and emission-free ferry fleet by 2050. To get there, we will expand the fleet by converting six existing vessels to hybrid-electric power, building 16 new hybrid-electric vessels and adding shore charging to 16 terminals.

The Ferry System Electrification Program is estimated to cost $3.98 billion. $1.68 billion is currently funded, including $1.03 billion from Move Ahead Washington and $599 million from the Climate Commitment Act (CCA). 

New hybrid-electric vessels

On July 1, 2025, Gov. Bob Ferguson announced that Eastern Shipbuilding Group was awarded a contract to build three new hybrid-electric 160-auto ferries. We received bids from two shipyards: Eastern Shipbuilding Group of Panama City, Florida and Nichols Brothers Boat Builders of Freeland, Washington. Eastern won with a bid of $714.5 million for the three vessels. Both bids were close to the state engineer’s estimate of $514 million for two vessels.

Jumbo Mark II vessels

In May 2025 we provided an update on the Wenatchee, which will return to service in summer 2025. Work to modernize the Wenatchee is nearly done, including the long-planned upgrade to its aging propulsion system, modernized ship controls, and conversion to hybrid-electric power. 

In March 2025, we announced that midlife upgrades and conversion work on the Tacoma and Puyallup will be delayed until after the 2026 World Cup. This change is part of Governor Ferguson and WSF's plan to restore service to pre-pandemic levels.

Terminal electrification

In collaboration with regional utilities, WSF is updating sixteen terminals to charge hybrid-electric ferries. We established memorandums of understanding with Seattle City Light and Puget Sound Energy to add power to the first five terminals: Bainbridge Island, Seattle, Clinton, Bremerton, and Kingston. Adding power involves routing new dedicated power lines and installing switchgear and a vessel charging system. Construction is currently anticipated to start in 2026 with Seattle and expected to wrap up in 2029.

Vessel charging system 

In 2024, WSF obtained industry feedback about the vessel charging system for the hybrid-electric fleet.

WSF released a request for proposals for the procurement of the vessel charging system on Jan. 21, 2025.

For a more in-depth look at our ferry electrification efforts, watch the extended video.