Project overview
This project will pave 7 miles for State Route 112 starting at milepost 0. Ten drainage culverts will be replaced from milepost 0 to milepost 8. Signage replacements between milepost 0 and milepost 41. This project also includes embankment repair work between mileposts 2 and 5.6.
What to expect
Culvert replacement work is complete. Crews will return to the project after the 2025/2026 winter to do some roadway patching. In August 2026, paving will begin.
The existing pavement is separated and cracking from multiple landslides and age. Signs are lacking modern safety standards and will need to be updated. Guardrail needs to be replaced or adjusted to conform to current safety standards. Non-fish bearing culverts become clogged, causing maintenance issues and water overflow onto the roadway and therefore need to be replaced.
Repair work at Rasmussen Creek and Jansen Creek is due to the winter storms that hit the area in 2022 and 2023.